We have been using the TRITON module in SCALE to perform a single point in time calculation with the NEWT discrete ordinates method (t-NEWT). The criticality calculation examined the unit cell at the beginning-of-life (BOL) meaning the cell had not been depleted or operated at power over a time. When a reactor is initially fueled, it has excess reactivity meaning that, in the absence of control mechanisms, it would be supercritical with a multiplication factor greater than 1.0. For our unit cell representing an infinite reactor, the multiplication factor was approximately 1.403209 at operating temperature at BOL. Naturally, the reactor isn’t operated in a supercritical condition. The excess reactivity is held down using control rods, chemical shim, and other burnable absorbers in the fuel to keep k = 1.0. As the fuel fissions, it has less reactivity. The plant operators then reduce the control mechanisms by withdrawing control rods, removing chemical shim and the burnable absorbers deplete as they absorb neutrons. At end-of-life (EOL) all of the control rods are withdrawn, and the burnable poisons have depleted and the chemical shim is removed. When the reactor can no longer maintain k = 1.0 it has to be shut down and refueled. Our unit cell model does not have control rods, burnable absorbers, or chemical shim. We could add a burnable absorber to the fuel and/or boric acid to the water. Adding control rods would be more of a challenge requiring the model be more representative of the assembly with a square array of unit cells with open cells for the control rod guide tubes. A typical example would be a Westinghouse 17 x 17 assembly. This text won’t get into a discussion of using SCALE for a unit assembly model until later chapters where we look at repeated lattice structures in SCALE.
For our problem, we will do a straight depletion of our unit cell without any control mechanisms in place. This will give us a good measure of how long the reactor could operate at full power if it were fueled with all new fuel rods of the same weight percent without leakage. When the depletion curve crosses 1.0, it represents the EOL for the reactor fuel. The number of days it takes to go from BOL to EOL represents the number of effective full power days (EFPDs) in this model. This model is simple as it assumes a constant power and temperature. The only values that are needed to add to our t-NEWT model are the time steps for depletion and the average specific power for the model. The units for average specific power are given in megawatts per metric tonne (1000 kg) of initial heavy metal (MW/MTHM) material. Assuming a large PWR operates around 3000 MW thermal and has around (17 x 17 x 177) or about 50,000 fuel rods each with a volume of around 210 cm a density of 10 gm/cm and 88% mass of U in UO the power density is around 32 MW/MTHM. Typical values for a large PWR are between 30 and 40 MW/MTHM.
An actual full core model would account for variations across all the fuel rods in each assembly and all of the assemblies (on order of 177 to 193) in the core. Each assembly will have a different position in the core and will have a unique flux and burnup history. The single unit cell is still useful for doing scoping calculations to understand trends and analyze effects of design changes quickly. Large, full-core, models will sometimes use single unit cells in detailed calculations and then apply the results to average values that represent the assemblies to speed up the calculations.
Example 3.4
Rewrite the unit cell problem in Example 3.1 for a TRITON depletion (t-depl) calculation. Use a specific power density of 35 MW/MTHM and deplete for the following depletion times of 2, 10, 50, and 15 steps of 100 days each for a total depletion of 1562 days.
Solution: Open the input file for Example 3.1. Change the t-NEWT to t-depl. The validation tab will turn red and there will be two warnings indicating that the input file is missing burnup and depletion information. Move the cursor to the line right after end cell data and use the CTRL + SHIFT to get the drop-down menu and select depletion. After you click enter, replace the comment, 'TODO: define depletion with 1. This indicates that material 1 (UO) fuel will be depleted. For our model, this is the only material that can be consumed.
After the depletion block is complete, move the cursor on the line after end depletion command and use the CTRL + SHIFT to get the drop-down menu and select burndata. Place the cursor between the begin and end burndata command and use the CTRL + SPACE to select cycle and the following default information will appear:
read burndata
power=40.0 burn=365.0 down=0 nlib=1 end
end burndataChange the default data to reflect the burnup steps specified in the problem statement. The down=0 statement indicates the number of days the reactor is at zero power after the burnup step. This is useful if you include a down time for decay following discharge but not needed for this problem so it will remain zero. The statement nlib=1 reflects the number of subintervals. Our problem will only have one. The final burndata card will look like:
read burndata
power=35.0 burn=2.0 down=0 nlib=1 end
power=35.0 burn=10.0 down=0 nlib=1 end
power=35.0 burn=50.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
power=35.0 burn=100.0 down=0 nlib=1 end
end burndataOnce the model is completed, we can go to the output file and retrieve the k-infinity values for each time step and record and plot the results.
| Time Step | Total Time | k-inf |
|---|---|---|
| 0 | 0 | 1.405365 |
| 2 | 2 | 1.367746 |
| 10 | 12 | 1.356093 |
| 50 | 62 | 1.340834 |
| 100 | 162 | 1.314479 |
| 100 | 262 | 1.277912 |
| 100 | 362 | 1.243256 |
| 100 | 462 | 1.210924 |
| 100 | 562 | 1.180493 |
| 100 | 662 | 1.151464 |
| 100 | 762 | 1.123490 |
| 100 | 862 | 1.096301 |
| 100 | 962 | 1.069736 |
| 100 | 1062 | 1.043728 |
| 100 | 1162 | 1.018261 |
| 100 | 1262 | 0.993360 |
| 100 | 1362 | 0.969130 |
| 100 | 1462 | 0.945669 |
| 100 | 1562 | 0.923109 |
We can see from the table and the following figure that the infinite reactor would operate for approximately 1225 days before it would no longer remain critical. This would be over 3.0 years. However, a real reactor is not filled with all fresh fuel at 4.5% enrichment and this model does not have leakage. For an actual PWR, it would need to be refueled every 18 – 24 months.
Notice how the depletion curve has a very sharp drop and then becomes nearly linear. This is due to the buildup of fission product poisons (mostly Xe and Sm) during the first 48 hours of operation. Once the fission products reach an equilibrium state, the burnup is nearly linear.
The output file has much more information besides criticality. For example, the end of the file has a burnup table that shows all the major nuclides and their concentrations. This includes both fission products and actinides. This data is useful for determining residual heat and radioactivity in spent nuclear fuel.